Here comes the cement mixer!

Heading into our second month of construction, and we’re making terrific progress! The few walls that define our open floor plan have been constructed. Underground plumbing work is complete, thanks to Tucker and his staff at TBH. Initial electrical has been accomplished by Don and his crew at Current Electric. Today (March 2) – filling in the trenches! Picking’s crew is pouring concrete as we speak, which is always fun to watch!